Dear FV,

 

On the tablet we are unable to save change process until an Actual Start and Actual Finish date have been entered.

 

Refer to the attached screenshot.

When setting up the workflow we must have an actual start and finish date.  

But we don’t need this completed until the task status is Complete.  If we want to manually enter a "Actual Start Date" then without an Actual Finish date, then we cannot save the task.   i.e. we need to note that a task was started yesterday, and is currently in progress.  

Please can you amend this to improve the functionality of Process Tasks.

  

 

  • Matthew Bailey-Lawrence
  • Dec 13 2016
  • Will not implement
Company Pacific Complete
Job Title / Role Quality Lead
I need it... Yesterday...Come on already
  • Attach files
  • Admin
    Betsie Hoyt commented
    February 01, 2019 16:28

    If you make the start dates and finish dates are made not visible then this resolves the issue.  We are however, looking at enhancements to processes to make them more user friendly.

Dear Viewpoint Suggestion Box contributor;

We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs. Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.

1515 SE Water Avenue, Suite 300, Portland, OR 97214 |  800.333.3197  | Contact Us | Terms of Use | Privacy | Support Policies

© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.